The Michigan Supreme Court issued an order on Nov. 20, in the case In re Implementing Provisions of Public Act 233 of 2023, on a request for leave to appeal from the below holding from the Michigan Court of Appeals. This case was filed by dozens of local governments challenging certain provisions of an order issued by the Michigan Public Service Commission (MPSC) concerning renewable energy legislation and local regulation. MTA’s Legal Defense Fund supported the case with an amicus curiae brief.
The Court of Appeals had affirmed some parts of the MPSC’s order and struck down other parts. Public Act 233 itself remained in effect. A summary of the Court of Appeals key holdings are as follows:
- Compatible Renewable Energy Ordinance: The Court of Appeals held that the MPSC correctly interpreted the statute to limit a CREO to only those provisions contained in Section 226(8). A CREO may not contain requirements in categories beyond those set forth in 226(8).
- Affected Local Unit: The Court of Appeals held that the MPSC incorrectly interpreted the statute to limit an “affected local unit” to only those municipalities with zoning jurisdiction. Instead, an affected local unit includes all local units of government where a proposed energy facility will be located, regardless of whether the local unit has zoning jurisdiction.
- Hybrid Facilities: The Court of Appeals held that the MPSC correctly interpreted PA 233 to allow for “hybrid” facilities, meaning that the total MW value of multiple renewable technologies can be combined to determine whether the MPSC can assume jurisdiction over a project. For example, a wind project could include solar components, and the MW values of both would be used to calculate the threshold for MPSC jurisdiction.
- Meeting Timelines: The Court of Appeals held that the MPSC incorrectly interpreted timing requirements for a meeting within the affected local unit. PA 233 requires that at least 60 days before the mandatory public meeting in a local unit, a renewable developer must offer to meet with the chief elected official of the ALU. Within 30 days of that meeting, the chief elected official must notify the developer whether the local unit has a CREO and is therefore required to file for siting approval with each ALU. The MPSC’s order slightly altered this to say that the chief official must notify within 30 days of the offer to meet, but the statute says within 30 days of the meeting itself.
- Administrative Procedures Act: The Court held that the MPSC’s order was not subject to the Administrative Procedures Act because it was merely an interpretive statement and/or establishing application filing requirements, both of which it has the authority to do without engaging in formal rulemaking.
The Michigan Supreme Court Order denied the local government application for leave to appeal. Items 1, 2, 3 and 5 above stand as decided by the Court of Appeals. The Michigan Supreme Court did, however, order oral argument on the request for leave from the cross-appellant MPSC challenging the decision in item 4. The Court asked for supplemental briefing regarding the following:
(1) whether the Court of Appeals afforded the Michigan Public Service Commission’s interpretation of MCL 460.1223(3), regarding the statutory deadline to be followed in which the chief elected official of an affected local unit (ALU) must notify an electric provider or independent power producer that the ALU has a compatible renewable energy ordinance (CREO), respectful consideration in accordance with the Court’s decisions in In re Complaint of Rovas Against SBC Michigan, 482 Mich 90, 103 (2008), and O’Halloran v Secretary of State, 515 Mich 606, 636 (2024);
(2) whether the Court of Appeals erred in reversing the Commission’s finding that an electric provider or independent power producer planning to construct a qualifying energy facility may proceed as if there is not a CREO if they do not receive a response within 30 days of an offer to meet with the chief elected official; or
(3) alternatively, whether a different interpretation of MCL 460.1223(3) should be adopted with respect to instances in which no elected official meeting is held or when such meetings face an unreasonable delay.